The contractors came on site on the 5th December and have had over two weeks to get things off to a flying start. As the photos show, the first stage was to create a compound to enclose the area planned for the extension and create a safe area for their machinery, site office, canteen and toilets.
The heavy machinery arrived on the 9th December and the site was cleared and levelled. The area of the new gym was dug out as the floor level will be slightly below existing floor levels, to give increased headroom in the gym.
On the 18th December things really started to get exciting as the foundations were dug out. On the 19th December the cement mixers arrived and the foundations are now in place.
In the meantime the specialist contractors have been on site starting the strip out of the existing changing rooms and showers. The ceilings are out and the walls come down in the new year.
Remember the football car park is available for use during the day to avoid having to compete with contractors vehicles coming on and off site.